June 10, 2025
Very little change in this week's update, other than uncooperative weather is pushing a few transition dates around on the Hwy. 63 project.
Please keep in mind that construction schedules are always weather dependent and are constantly subject to change.
Foster and Grove: We're still waiting for the finish work around manholes, which are still low and marked with cones. It should occur in the next week or two.
1st and Marshall: Work on these two blocks behind the Elementary School is scheduled to begin the week of June 23rd. The exact order of operations will be determined in the coming weeks.
Highway 63: Concrete work on the west side of the north/south portion of Hwy. 63 should wrap up this week or very early next week. Mid- to late-week next week they will transition to the east side of the downtown and north/south portion of the corridor-starting with traffic control and saw-cutting, followed by curb, gutter and sidewalk removals. All new curb in this area should be installed prior to the 4th of July holiday weekend (but not sidewalk). Following the 4th of July, work will shift to the mill and overlay of the highway driving surface to allow for street light work on the east side downtown. Sidewalk work on the east side is currently comtemplated to commence around the week of July 21st. Some work on the concrete on the east/west portion on Hwy. 63 is occuring this week. We're still hopeful that all the concrete work downtown can be completed by Rutabaga--but no firm promises from the contractors due to the unknown of Mother Nature!