Please ensure Javascript is enabled for purposes of website accessibility

May 20, 2025

 

Please keep in mind that construction schedules are always weather dependent and are constantly subject to change.

 

Foster and Grove: With the exception of some work around manholes, work on these streets is substantially complete.

 

Arcade and Hunter: Resurfacing will be completed this week.

 

Highway 63: Concrete crews plan to return Thursday of this week (May 22nd) to begin installation of pedestrian curb ramps at the corners on the west side of the highway downtown. Either late this week or next week just following Memorial Day, sidewalk installation on the west side downtown will begin--with work once again commencing at the Four Corners and moving northward. Sidewalk installation will occur at a rate of approximately one block per week. And finally, the remaining curb installation on the west side of Hwy. 63 will also occur next week--currently planned for May 28th or 29th. It's important to note that certain sections of sidewalk may remain temporarily unpoured to leave space for installation of new lightpole bases. When and where this does occur, gravel and/or rubber matting will be used to make the sidewalks passable.

 

Thanks to everyone for your patience as this important and valuable work occurs!

May 13, 2025

 

Hwy 63 (from Water St. to Veteran’s St.) will be closed on Saturday, May 17 to replace water service to the Elementary School.

 

Foster & Grove: Final resurfacing will be completed Tuesday, May 13.

 

Hunter & Arcade: Hunter (from Western to Arcade) and Arcade (from Hunter to Lake) are being resurfaced with a mill and overlay treatment. No parking on these blocks the weeks of May 12 and May 19.

 

Hwy 63: Curb, gutter and sidewalk removals on the west side of the downtown business district heading north continue this week. New curb is being installed in this section now. Sidewalk installation will follow shortly thereafter--planned for the week of May 19th. Mirror image work on the east side of the downtown business district should commence just after Memorial Day.

May 6, 2025

 

Foster & Grove: No parking May 8th from 2nd to Arcade as they prepare the roadway for final resurfacing the following week. Exact dates of final resurfacing are TBD.

 

Hunter & Arcade: Hunter (from Western to Arcade) and Arcade (from Hunter to Lake) are being resurfaced with a mill and overlay treatment. No parking on these blocks the weeks of May 12 and May 19.

 

Hwy 63: Curb, gutter and sidewalk removals on the west side of the downtown business district began this week. This work should wrap this week. New curb installation in this section should begin Monday May 12th, with sidewalk following shortly thereafter--now planned for the week of May 19th. Mirror image work on the east side of the downtown business district should commence just after Memorial Day.

April 30, 2025

 

Sidewalk removals in the downtown business district will begin next week. Business and property owners will need to remove personal property (i.e. benches, pop machines, etc.) from the sidewalks to accommodate the work. Thanks for your cooperation. Things are about to get real, but we'll get through this together!

April 29, 2025

 

There will be no parking on Foster and Grove Streets between 2nd and Arcade Avenues on May 8th as contractors will be preparing these streets for the final installation of blacktop the following week (the exact date for blacktopping is TBD). Please plan accordingly. We will do our best to keep you informed on the date for final blacktopping.